Saddleworth School Progress

Further good progress is made on site for the erection of Saddleworth School.

News | Author: Becky Hunt

IMG_5805

Further good progress is made on site for the erection of Saddleworth School. Despite some challenging weather conditions in an exposed site, Tilbury Douglas (recently rebranded - previously called Interserve) have been maintaining a very organised site whilst keeping to programme!

The steel frame is now complete to all 4 phases. Concrete is being poured, having completed phase 1 and commencing phase 2 this week. At the same time the SFS is also being installed with phase 1 completed this week (8th march) and Phase 2 starting next week (15th March). It’s been a great team effort and the result is evident!

Credit: Anastasia Kapagerof & Annie Kwan, jmarchitects Manchester