Seona Reid Building, Glasgow School of Art
The design is of international quality and reflects the unique character and aspiration of the Glasgow School of Art as a cultural institution.
Date
2014
Client
Glasgow School of Art
Value
£30m
The planning and design of the building is highly complex given the range of requirements for bespoke designs for each department and spatial flexibility. We managed series of workshops to establish the detailed functionality of every space in the building, and provided interactive 3D visualisations of our designs to assure end-users that they have everything they need to accommodate their unique working requirements.
A robust exposed concrete frame and massive shuttered concrete interior walls are contrasted by a lightweight translucent façade treatment that complements the heavy stone façade of the existing iconic Mackintosh masterpiece opposite. Old and new are then unified by a significant development of the public realm between the two buildings, providing a much enhanced setting for both.
See videos of the project by Spirit of Space below.
Project gallery
Below are a selection of images from this project along with a description. Tap an image and it will appear fullscreen with a close button. There will also be the option to view the next image in the gallery.
The Challenge
GSA aimed to significantly enhance the teaching, learning and research facilities available to its students and staff, whilst providing access to public spaces including galleries and the Simon Sainsbury Mackintosh Interpretation Centre. Phase 1 of a larger campus redevelopment is a new undergraduate school for all design courses.
The Solution
The concept of the building includes “circuit of connections,” a central ramped circulation pattern interlinking the various levels from the basement lecture theatres, past ground floor main entrance and second floor social and dining areas, to the various levels of studio spaces above.
The Outcome
All pre-contract timescales and deadlines were met and funding was successfully achieved on programme. In addition, by ensuring that the design and construction sequence incorporated comments raised by affected parties, the project acknowledges local issues in terms of working hours, routes to site, safeguarding local issues and improvement.
Related Projects
Greater Manchester Institute of Technology
Greater Manchester Institute of Technology The University of Salford and core partners have developed a new Greater Manchester Institute of Technology (GMIoT) within the University campus....
Inspire Academy SEND
New build Free School, Secondary Inspire Academy is a project for a new build SEND school for pupils aged 11-18 in Gillingham to provide 160 urgently needed places for Medway Council. The scheme provides 90 SEMH spaces and 70 ASD spaces.
Thistle Primary School
The Thistle Primary School is a new primary school incorporating accommodation for 801 primary school pupils incorporating community facilities and a full-sized 3G pitch, designed to meet the Net Zero Public Sector Building Standard.