Alton Road has been progressing well since the last update. The concrete frame has been completed on two of the blocks, with the roof of the third almost finished as well. It has been great watching the frame going up and seeing the views improve at every floor – the residents are going to have some wonderful sights and might not be able to leave their windows! It’s been a busy month in the ‘office’ preparing various pieces of information for the contractor and assisting with queries for procurement of window and door packages. The Metsec frame is currently being installed, with the brickwork following in the next couple of weeks. With lots of deadlines it has been great help getting some additional support from the Edinburgh office and others in London. We’re learning a lot about installing zinc cavity trays and ensuring all the changes in Regulation 7 have been accounted for.
Related News
Bolton Market Site Visit!
jmarchitects just visited site to witness the fast progress of the new steelwork installation, whilst ground is being prepared for the structural floor slab! It’s so great to see it all taking shape!
The Linen Quarter shortlisted in the Residential – Multi Unit category at the Scottish Design Awards
The Linen Quarter at Pilmuir Works is a new residential community created within the restored Category A-listed former Damask linen factory, previously on the Historic Environment Scotland’s Buildings at Risk Register.
Welcome to Princess Street!
The Manchester Studio is ecstatic to have Ben Wigley join the Studio as a Senior Architect.